Incident timeline
- 14:00: Failure of the Radascan reported by the client
- 14:05: The SMS technical team connected with the vessel and collected alarms and system status
- 14:10: Case escalated to the SMS General Manager, a Guidance Marine-trained engineer (2011) with extensive experience on Cyscan and Radascan View. A likely hardware fault was identified on the Radascan sensor
- 15:00: Vessel confirmed off-hire and returning to port. SMS committed engineer attendance with the required spares
- 15:30: Critical spare parts for the sensor arranged and dispatched with a service engineer
- 22:00: Vessel alongside. SMS engineer boarded immediately
- 24:00: Faulty hardware replaced inside the sensor, system tested and Radascan restored
Result
Full operational recovery within 10 hours. The vessel returned to on-hire with minimal downtime.
Key success factors
- Immediate technical response (within 5 minutes)
- Accurate remote diagnosis by an OEM-trained engineer
- Readily available critical spares
- Efficient logistics and mobilization
- Same-day onboard intervention
- Reduced commercial loss for the client
For mission-critical DP and position reference systems, downtime is far more expensive than hardware replacement. The difference lies in correct diagnosis and speed of execution.