2025 Final Project Successfully Completed

Sinor Marine Services (SMS) has successfully completed and signed off a major project in 2025, including Sea Trials and FMEA Trials, delivered on schedule.

Despite an extremely tight global project timeline, SMS delivered with zero delays, and the project concluded with full customer satisfaction.

Project scope

  • Supply, installation and commissioning of the Sonardyne Ranger 2 system with hull-through deployment machine and DN500 gate valve with actuator
  • Supply, installation and commissioning of the SMT MK2 Taut Wire system
  • Supply, installation and commissioning of the Fugro OceanStar DGPS
  • Supply, installation and commissioning of the Clear-Com communication system

We thank our customers, our OEM partners and the SMS team for their collaboration and support throughout 2025.